Commercial tenant improvements (TIs) are the alterations that turn leased space into space your business can run in. The lease, the design, the permit and the construction schedule all depend on each other, and the cheapest way to lose months is to treat them as separate jobs. Under a design-build contract, one team handles design and construction from the first walkthrough, so scope and budget are settled together before the permit goes in. American Companies has worked this way since 1980, and tenant improvements are one of the services we deliver through our design-build construction practice.
This guide is for owners and managers who have signed, or are about to sign, a lease and need to know what the work involves, what to settle in the lease, and what to expect from permitting.
Key Takeaways
- Tenant improvements are alterations to leased space negotiated as part of the lease. They usually become the landlord’s property when the lease ends.
- The work letter and allowance terms in your lease set your real budget. Settle them before you design, not after bids arrive.
- Permits, inspections and a certificate of occupancy sit on the critical path. Early coordination with the building department protects your opening date.
- Design-build keeps design, pricing and construction under one contract, which is how scope and budget decisions stay coordinated.
Table of Contents
- What commercial tenant improvements are
- What the work usually includes
- Settle the lease terms before you design
- Budgeting: allowance, cost drivers and contingency
- Permits, inspections and the certificate of occupancy
- What drives the schedule
- Why design-build suits tenant improvements
- How American Companies handles tenant improvements
- A short checklist before you sign
- FAQ
- Sources
What commercial tenant improvements are
A tenant improvement is an alteration, renovation or customization to a leased property that is negotiated as part of the lease. According to Pulley’s landlord guide, TIs cover permanent or semi-permanent changes such as flooring, ceilings, lighting, HVAC, electrical and plumbing. They revert to the landlord at lease end. The same guide treats tenant-owned furniture, fixtures and equipment (FF&E) as separate from TIs, and it leaves landlord-owned core systems such as the roof, structure and elevators outside the tenant’s scope.
Two terms come up constantly:
- Build-out. Often used for finishing a raw or second-generation space for a new occupant. In practice, build-out and tenant improvement describe the same kind of work, and your lease will use one or the other.
- Renovation. Usually means upgrading space you own or are already occupying. A TI is defined by the lease relationship: someone else owns the building, and the lease decides who pays and who keeps the result. If you own the building, our guide to planning an office renovation is the closer fit.
What the work usually includes
Scope depends on the business, not just the square footage. Typical scopes by use:
| Business type | Common TI scope |
|---|---|
| Professional office | Demolition, new partitions, ceilings, lighting, data and electrical, restrooms, reception and break rooms |
| Medical and healthcare | Plumbing at exam rooms, specialized electrical, infection-control finishes, code-driven corridors and egress |
| Hospitality and retail | Storefront and entry changes, kitchen or back-of-house infrastructure, finishes, signage coordination |
| Industrial and light manufacturing | Office build-out inside a warehouse, power upgrades, HVAC, floor and loading modifications |
Healthcare tenants face the heaviest regulatory load. Our overview of healthcare construction for owners and developers covers what changes when the space serves patients. For tenants in professional offices, the decisions center on layout, acoustics and how people move through the suite.
Settle the lease terms before you design
The lease decides who pays for what. Husch Blackwell’s tenant guide to lease negotiation recommends confirming four things before you sign:
- Delivery condition. What state the landlord hands you the space in, and which work is the landlord’s versus yours.
- Allowance amount and eligible costs. The tenant improvement allowance is the landlord’s contribution toward the build-out. Specify in the work letter whether soft costs such as design fees and permits qualify.
- Draw mechanics. How and when you are reimbursed: on completion, in progress payments, or against paid invoices.
- Change orders and excess costs. Define your approval rights so a change cannot be pushed to you without your consent.
The work letter is the lease exhibit that spells out the landlord’s and tenant’s construction responsibilities, and it deserves as much attention as the rent. A contractor who reads it before pricing can tell you where the allowance will run out.
Bring the builder in before the lease is final
Most tenants call a contractor after signing, then learn the allowance, the delivery condition or the work-letter deadlines do not match the space. A design-build team can walk the space, test your program against the building’s systems and give you a realistic budget range while you can still negotiate. That is the practical meaning of design and construction professionals working together from the start: the person drawing your layout is also answerable for what it costs to build.
Budgeting: allowance, cost drivers and contingency
Allowances are usually quoted per rentable square foot and often fall short of the full cost of a build-out. Treat the allowance as a floor for planning, not a ceiling for the budget. Build your estimate from the scope:
- Condition of the space. Second-generation space with existing walls and ceilings costs less to convert than a raw shell.
- Mechanical, electrical and plumbing work. Moving HVAC zones, adding panels or running new plumbing lines is where budgets move most.
- Specialty rooms. Server rooms, kitchens, exam rooms and conference suites carry higher per-foot costs than open work areas.
- Code-triggered upgrades. Accessibility, fire protection and egress work can be required when the scope reaches certain thresholds.
- Soft costs. Design, engineering, permit fees and inspections. If the lease does not make them allowance-eligible, they come out of your pocket.
- Contingency. Existing conditions behind walls and above ceilings are rarely fully known before demolition.
Published per-square-foot averages vary widely by market, by building class and by what each study counts in its model project, so they are poor substitutes for a priced scope on your own space. Ask for a budget broken out by trade and by landlord-eligible versus tenant-only items. Our construction management approach keeps those numbers visible throughout the job, so you can see at each stage how the allowance is being drawn.
A worked example of how the allowance gets used
Suppose a tenant is offered an allowance and plans a suite with private offices, a conference room and a break room. The landlord’s work letter reimburses hard construction but excludes design fees and permit costs. Without reading that line early, the tenant budgets the full allowance toward construction and then discovers a gap at the end. With the exclusion known in advance, the tenant negotiates to include soft costs, or sets aside cash for them before the design is finished. Either way, the surprise is gone before drawings are issued.

Permits, inspections and the certificate of occupancy
Nearly every tenant improvement that touches walls, electrical, plumbing, mechanical systems or egress needs a permit from the local building department. Requirements differ by city and county, so confirm with your jurisdiction. As one example of the pattern, the City of Olympia, Washington publishes a commercial tenant improvement checklist that explains when a certificate of occupancy is issued and when a given permit type does not produce one. Your own city will have its equivalent.
The sequence is consistent across most jurisdictions:
- Design and permit drawings. An architect and engineers prepare plans for the scope.
- Plan review. The building department checks the plans against code. Corrections are common, and each round adds time.
- Permit issuance and construction. Inspections happen at stages such as framing, rough-in and final.
- Final inspection and certificate of occupancy. You generally cannot open until the jurisdiction signs off.
A change in how the space is used, such as converting office space to a clinic or a restaurant, is where code requirements tend to expand. Plan on the building official asking about egress, fire protection and accessibility when the use or the scope changes materially.
This is where early coordination with municipal officials pays off. Our process includes it from the start, so questions about use, zoning and code are raised during design rather than after plan review comes back with comments. If your project is tied to a plan commission review, that coordination matters even more, because the commission’s timeline can drive the construction schedule.
What drives the schedule
Most TI schedules lose time in the same places:
- Lease and work-letter negotiation running long, so design starts late.
- Design changes after pricing, because the program was not locked.
- Plan review comments that require redrawing and resubmission.
- Long-lead items such as electrical gear, rooftop units, storefront systems and specialty equipment.
- Hidden conditions found at demolition.
- Inspection scheduling and failed inspections that require rework.
You cannot eliminate all of these, but you can sequence them. Order long-lead items as soon as drawings allow, submit permit drawings complete rather than in pieces, and keep one party responsible for design and construction decisions. Our guidance on avoiding common construction mistakes covers several of these patterns from the owner’s side.
Why design-build suits tenant improvements
TI projects are short, tight and tied to a lease commencement date or a business opening. In a traditional split, the architect designs, a general contractor bids, and the price often comes back over budget after the design is done. Redesign follows, and the schedule slips.
Design-build puts designers and builders on one contract. Pricing happens while the design develops, so a decision to move a wall or upgrade a system comes with its cost and schedule effect at the time you make it. You deal with one team, which means direct communication and personalized project management rather than relaying questions between firms.

For business owners who need more space, manufacturers adding offices inside a plant, hospitality operators fitting out a new location or senior living and multi-family developers finishing commercial amenity space, the same logic applies. Fewer handoffs mean fewer places for scope, cost or schedule to be lost.
How American Companies handles tenant improvements
American Companies is a family-owned design-build firm founded in 1980, serving manufacturing, hospitality, healthcare, retail and other commercial sectors. Tenant improvements sit alongside our building renovations, facility additions and adaptive reuse work. We pair architectural design with construction management, so the plan that wins your landlord’s approval is the plan we price and build.
If you have a lease in hand or a space under consideration, we can review the scope with you before the work letter is final. Start with our design-build construction page.

If you are also weighing a purchase or a build-to-suit arrangement instead of a lease, our real estate development team handles acquisition and phased development design as well.
A short checklist before you sign
- Get the landlord’s delivery condition in writing, including which systems are in working order.
- Confirm the allowance amount, eligible costs and how it is paid out.
- Check deadlines in the work letter for plan submission and for using the allowance.
- Have a builder review the space for existing conditions before the lease is final.
- Ask the building department what permit type and inspections your scope needs.
- Identify long-lead equipment and set order dates against your opening date.
- Define who approves change orders and who pays for overruns.
FAQ
Is a tenant improvement the same as a renovation?
Not exactly. A tenant improvement is work in leased space that the lease addresses: who pays, who approves and who keeps it at the end. A renovation is the broader term and often refers to upgrading space you own. The construction methods overlap, but the lease terms are what make a TI different.
Who pays for commercial tenant improvements?
It depends on the lease. Landlords commonly provide an allowance toward the work, and the tenant pays costs beyond it. The work letter should state which costs are eligible, such as design fees and permits, and how the allowance is reimbursed.
Do tenant improvements need a permit?
Most do, particularly when they involve structural, electrical, plumbing, mechanical or life-safety work. Cosmetic work like paint may not. Requirements vary by city and county, so confirm with your local building department before work begins.
How long do tenant improvements take?
The time depends on scope, plan review in your jurisdiction, lead times for equipment and any hidden conditions. A simple office refresh and a medical or restaurant build-out are very different projects. A builder who reviews your space and drawings can give you a schedule tied to your actual scope.
Sources